launching of the longitudinal beams has commenced and is at finishing stage, also the placement of deck slabs and reinforced concrete beams work ongoing simultaneously
Speaking while inspecting the project the chairman lauded the contractor for the milestones attained on the project, he however urged the contractor to speedy up work for the timely completion of the bridge work.
He was accompanied by the secretary of the board, Engr. Sampson Igodo, board members, engineers among Others
https://www.facebook.com/groups/1418911 ... 7S9Ucbxw6v
The chairman, Directorate for Project Monitoring and Evaluation Bayelsa State, Hon. (Engr.) Ebiye Tarabina, Mcoren recen
-